New valeting building

The Client: Omni Investments LTD

The Project: New Valeting building & additional parking spaces

  

   

New build Design & build

The location: Carriers Road, Derby

The challenge: Working around a busy operational business & dealing with a high water table when constructing the foundations & drainage

The solution: Organising ‘Just-in-time’ deliveries, clear communications with existing business

The result: Project completed 4 weeks early. Seamless construction process delivering additional and upgraded space for commercial premises

Skills/ services offered: PM, Organisational management, good quality sub-contractors & suppliers